| Location: | Mpumalanga Province, 7km south-west of the town of Steelpoort |
| Ownership: | 100% Sylvania Platinum |
| Comprises: | Chrome tailings re-treatment plant recovering chrome concentrate and PGM flotation plant recovering PGM concentrate |
| Safety record: | No serious safety incidents to date |
| Access and infrastructure: | Short dirt road connecting complex directly to the R555 regional highway; national railway grid |
| Feed sources: | Lannex chrome tailings dump and current arisings from the nearby Lannex Plant (Spitzkop and Broken Hill mines also to contribute primary mined chromite ore to Lannex in the future) |
| Production capacity: | 25,000 tonnes of tailings materials over a six-month period (Please refer to Appendix 5 of the latest Venmyn Competent Person’s Report) |
| PGM prill split: | Pt=58.0%, Pd=25.5%, Rh=16.5%, Au=0.0% |
| First year of full operation: | 2009, ramp up to full production: 2011 |
| Production figures: | Please refer to Sylvania’s latest quarterly results |